2.26 freeze in a little over a week
Carlos O'Donell
carlos@redhat.com
Mon Jun 26 23:34:00 GMT 2017
On 06/23/2017 03:59 PM, Joseph Myers wrote:
> On Fri, 23 Jun 2017, Siddhesh Poyarekar wrote:
>
>> On Thursday 22 June 2017 11:18 PM, Palmer Dabbelt wrote:
>>> We're not upstream in Linux yet, we're also in the process of submitting
>>> patches. We've been through two rounds of review of the ABI on the Linux
>>> mailing list and there weren't any comments the second time.
>>>
>>> We've committed to maintaining ABI stability with the first one to get released
>>> (which would be glibc if we can get into 2.26).
>>
>> We usually wait for the kernel bits to go in before releasing a glibc
>> with the new ABI, but I'll defer to Carlos, Joseph, etc. on that.
>>
>> Provided that is clear, I think it should be safe to continue reviewing
>> the patchset until about a week or two before the release date
>> (tentatively 1 Aug) and then take a call on whether it is ready or needs
>> to be pushed to 2.27. Given that it does not interact with other
>> architecture code, their testing should not get affected.
>
> I'm wary of adding new ports without a clear timescale when we can expect
> them to be buildable with build-many-glibcs.py using normal upstream
> sources of other components.
>
> Has the Linux kernel port been accepted subject to at most minor changes
> relative to the latest version, with good reason to expect it will be in
> Linux 4.13? Is the port in linux-next, or will it be within the next
> month? If the glibc port won't be buildable with Linux 4.13, that's
> leaving a long time with a new port people can't build when making bulk
> changes.
I agree with Joseph.
We need to see some fairly clear intent from the Linux kernel side before
adopting a new port, and we like the kernel side to land first before
glibc. This ensures the ABI work is done with time.
--
Cheers,
Carlos.